As we continue to grow as a global brand, we are currently experiencing increased demand which has resulted in temporary delays in production timelines.
Please be assured that this is a short-term challenge, and we already have measures in place to improve and expand our production capacity. We remain fully committed to delivering the highest level of quality and service throughout this period of growth.
To help minimize potential delays or disappointment with your clients, we kindly ask that you place orders as early as possible and not hold them back, allowing us the maximum production time to fulfill them efficiently.
Please note the following temporary lead time adjustments based on plated trim finishes:
Non-PVD finishes: please allow 12-14 weeks lead time
PVD finishes: please allow 20-24 weeks lead time
Our rough valving will continue to be available as normal.
If you have any orders with particular urgency, we encourage you to communicate this directly with our Purchasing Department. We will do our very best to realistically support your deadlines wherever possible.