| Non-stocking (Custom) lead times are 16 weeks and contingenton the container schedule, not when an order is placed. |
![]() |
Claybrook Container Schedule
Maax Decrease 5/23/25
As announced on April 30th, and a part of the ever-changing environment of IEEPA tariff rates between the US and China, we previously implemented increases in response to the federal recovery action. While federal tariffs between the US and China are still a reality, the ongoing negotiations have allowed us to walk back some of the list price impact. We realize the pain in managing changes in pricing, but want to pass this action along as swiftly as possible. For that reason, we will be implementing these reductions effective today, May 23, 2025. These adjustments will affect tubs and bases only; doors will not be reduced at this time.
Please read the following important information carefully, as it may affect your business:
- Bases and Tubs produced in China previously increased by 14.9% will now be reduced to a 9% increase. Net reduction from original increase is 5.9%
- May 23, 2025, new pricing in effect and posted online, including adjustments to those impacted by the reduction associated with tariff federal recovery adjustment only on products produced in China.
Clarifying Details:
- All products made in Canada* or the USA and are USMCA certified are not currently subject to any market tariffs. Therefore, no federal recovery action will be applied to these products, and operations will continue as usual.
- AcrylX product categories, currently, are excluded from the federal recovery actions.
Basco 6/1 Price List
LG Promo Calendar 5/19/25
Viking Updates
Marketing Update | Moen | May 2025
Bosch/Thermador Lead Time Updates 5/1/25
Hello and Goodmorning. Here is a quick update for our Bosch & Thermador Lead times -Summary of our key inventory for the top SKUs. These are all Estimated based off the current timeframe we are in. As you well know these dates can change with the climate of the industry and the current challenges of the tariff discussions.
- Refrigeration-All models in stock by end May. Did not see any exceptions.
- Dishwashers-most models to be in stock by mid June. Exceptions Bosch SHP78CM5N end of June, SHE53C85N mid July, SHV53CM3N mid August, Thermadorà DWHD640EFP Mid July, DWHD640EPR end of August
- Ovens & Ranges-most models to be replenished by April (model HMD8454UC, HBL8753UC by early June, HMC80252UC mid June)
- Note MC30WP, MC30WS, HMB50152UC & HMC80252UC any orders placed for these models after 5/1 will have a 4 month delay
- Surface & Ventilation all models in stock by June ( HUI30253UC available in August)
- Laundry-no issues
- Built in Coffee-no issues
IN STOCK DISHWASHERS!
The new Bosch 800 series SHV78DM3N has stock in our warehouse right now. This model is the 800 series WITHOUT the power control spray arm. If you have the a customer in need of a panel ready, we have these ready to go!
Additionally, SHP65CM5N is back in stock in great number. We have over 2000 fresh out of the factory ready to go! These will be the best option for quick turnaround in the panel ready and pocket handle for our brands right now. The rest of our models should be following suit very quickly. Thank you for supporting our brands! Have a great week ahead!
Oceania Lead Time Update

We would like to inform you that freestanding baths from the Authentik Signature Series, as well as baths equipped with an air jet system, are now produced with a lead time of 4 weeks.
This adjustment reflects the current composition of our production team, combined with the growing demand for our North-American Made products — a level of enthusiasm that speaks to the trust you place in us, and that we truly value.
All other product categories maintain a standard lead time of 2 to 3 weeks. When multiple items are included in a single order, delivery timing may be adjusted to ensure the most efficient shipping process.