Subject: Robern Lead Time Report – June 30, 2022
• We are currently at a 24-48 business hour response time.
Please see attached for an update on Craft Series inventory.
| Category | Product | Model # | Ship Date | Back to Normal Lead Time |
| Medicine Cabinets, Vanities, Lighting, Mirrors | Profiles – Matte Gold | TBD | TBD | |
| Vanity Accessory | Glass Hair Organizer | VAHAIRORG | TBD | TBD |
| Vanity Tops | Bodo/Skaarsgard Integrated Top – 36” W | TA36MCO102-8CS8 | Shipping 2nd week in July; and shipping additional units 2nd week in August – orders submitted through 4/29 between both shipments.Additional units tentatively shipping 3rd week in September and 3rd week in October. | TBD |
| Medicine Cabinets | Profiles – 48” H Polished Nickel | End of July | End of July | |
| Mirrors | Sculpt – 25” W x 31” H Slim and 27” W x 33” H Chamfer | Second week of July | Second week of July |
Classic and Inspire finishes, Profiles vanities, and Engineered Stone Tops are at a 4-week lead time.
All other cabinets, wall mirrors, vanities in the Essentials finishes, lighting, and glass tops are at a 2-week lead time. To review standard lead times, visit here.