Robern Lead Time Report – June 3, 2022

Robern Customer Delight Team

•        We are currently at a 24-48 business hour response time.

Please see attached for an update on Craft Series inventory.

CategoryProductModel #Ship DateBack to Normal Lead Time
Medicine Cabinets, Vanities, Lighting, MirrorsProfiles – Matte Gold TBDTBD
MirrorsVitality – Inset – 24” W x 40” HYM2440RIFPD3Shipping now – orders submitted through 4/15; Continue shipping – middle of JuneMiddle of June
Vanity AccessoryGlass Hair OrganizerVAHAIRORGTBDTBD
Vanity TopsBodo/Skaarsgard Integrated Top – 36” WTA36MCO102-8CS8Shipping 1st week in July; and shipping additional units 1st week in August – orders submitted through 4/5 between both shipmentsTBD

Classic and Inspire finishes, Profiles vanities, and Engineered Stone Tops are at a 4-week lead time.

All other cabinets, wall mirrors, vanities in the Essentials finishes, lighting, and glass tops are at a 2-week lead time. To review standard lead times, visit here.