Americh UPDATES: May 1st price list, lead times

A quick update on a few things. 
 
Price list – The May 1st price list is almost finished.  Americh is reviewing the final version and expect a PDF copy to be available within a week.
 
Both factories – Both factories (California & Charlotte) are working at capacity.  Americh is stable with raw materials at this point and working hard to keep the flow constant.   Pricing has not yet stabilized though.  We are hoping the increases will slow.
 
Lead times – Americh is extending their standard lead times slightly. They are 1 week longer than standard, therefore not too bad compared to others.
                                                                         
                             Old Lead               New Lead Time

Individual Soaker tubs/Shower Bases                                   2 weeks              3 weeks

System tubs – Whirlpool, Airtubs, Anex, Serenity               3 weeks              4 weeks

Individual ROC tubs Individual soaker tubs                          4 weeks              4 weeks 

Individual Acrylic freestanding tubs                   4 weeks              5 weeks  

Individual Gelcoat freestanding                  6 weeks              8 weeks

Stock orders and Projects: Will be quoted on a case by case basis, generally 4-6 weeks

I thank you for your continued support of Americh and let me know if I can help in anyway.