Robern Lead Time Report – August 5, 2021

Robern Customer Delight Team

  • We are currently at a 72 business hour response time for all email boxes. You will likely experience delays versus our normal response time. Please do not email again to follow-up.
CategoryProductModel #Ship DateBack to Normal Lead Time
Medicine CabinetsUplift Tech – Electric, Electric+ 1st week in AugustEnd of September
Medicine Cabinets & MirrorsMain Line – Bryn Mawr & Rosemont – Brushed Black  2nd week in August3rd week in August
Medicine CabinetsM Series – 24” W x 40” H – Arch   2nd week in August2nd week in August
MirrorsVitality – 48” W x 36” H Mirror (Flip) – Inset LitYM4836RIFPD3P3rd week in August3rd week in August
MirrorsVitality – 24” W x 30” H Mirror – Column LitYM2430RCFPD42nd week in August2nd week in August
MirrorsVitality – 30” W x 40” H Mirror – Perimeter LitYM3040RPFPD32nd week in August2nd week in August
MirrorsSculpt – 31” W x 41” H (Slim) and 33” W x 43” H (Chamfer) Mirrors 2nd week in August2nd week in August
LightingVesper – Edgeline – 36” and 40” HGLA36ELPS3D, GLA40ELPS3D2nd week in August2nd week in August

Classic and Inspire finishes, Profiles vanities, and Engineered Stone Tops are at a 4 week lead time.

All other cabinets, wall mirrors, vanities in the Essentials finishes, lighting, and glass tops are at a 2 week lead time. To review standard lead times, visit here.